Week 3 Update

Most of the demo throughout the golf course is complete, the pump station has been connected to the new mainline that has been installed through 13. Preliminary shaping is nearing completion on holes 11, 12, 13, 17, and 18. Enjoy the video update this week showing some of the shaping process!